Background:
The
Project was initially planned as a combined-cycle power generation plant
(the Original Project). In late 2004, BayCorp purchased the
development rights to the Original Project. Due to the increased interest
in renewable energy in Texas
and the location of the site in a heavily forested area of
Texas,
BayCorp decided to pursue the project as a biomass plant. Shortly after deciding to develop
the project using biomass as fuel, BayCorp engaged R.W. Beck to conduct a
feasibility study and they concluded that a 100 MW biomass power plant was
feasible and BayCorp and EMI
decided to jointly pursue the development of the
projec
|